Centering, shuttering or formwork is a sort of temporary construction provided for laying cast-in-situ concrete to required shape. A good formwork should satisfy the following requirements.
· It should be strong enough to
withstand all types of dead and live loads such as self-weight, weight of
reinforcement, weight of wet concrete, loads due to workmen, construction
equipment, other incidental loads and forces caused by placement and
consolidation of concrete, imposed upon it during and after casting of
concrete.
· It should be rigidly constructed and
efficiently propped and braced so as to retain its shape without undue
deflection.
· The joints in the formwork should be
tight against leakage of cement grout.
· The material of the formwork should
be cheap, easily available and should be suitable for reuse several times.
· The formwork should be as light as
possible.
· The formwork should rest on firm
base.
· The material of formwork should not
wrap or get distorted when exposed to sun, rain or water during concreting.
ECONOMY IN FORMWORK
It may be noted that the total cost of concrete construction includes the
cost of formwork as well. Construction of formwork involves considerable
expenditure in terms of cost of material, cost of labour for fabrication, erection
and removal of formwork and time element. In case of buildings, the cost of
formwork may range between 30 to 40% of the cost of concrete work. In case of
special structures like bridges, all chimneys, dams etc. the cost of formwork
may range between 50 to 100% of the cost of concrete work, or even more. Since
formwork contributes nothing towards the stability of the finished structure,
it cost should be kept barest minimum consistent with safety.
· The building should be planned in
such a way that there are minimum number of variations in the size of rooms,
floor area etc. so as to permit re use of the formwork moulds repeatedly.
· The scheme of the formwork should be
efficiently planned and suitably designed to determine the most economical but
safe sizes of different components including the supports or props.
· The formwork should be constructed in
such a way that timber is cut to the minimum and it can be struck off with ease
and re used with least damage.
The quality of finished concrete surface depends to a great extent upon
the quality of formwork used in the work. In case, the formwork is made out of
rough timber and is not constructed properly, the resultant concrete surface
will be irregular and full of defects.
This to effect economy, the formwork should be made with good quality
material and should be constructed properly, besides following the steps
referred above.
MATERIALS FOR FORMWORK
Formwork can be made out of timber, plywood, steel, precast concrete or
fibre glass, used separately or in combination. The type of material to be used
for formwork depends upon the nature of construction as well as the
availability and cost of material. In early stages, formwork was made up of
timber alone. With the introduction of steel forms, use of timber former is
getting reduced specially in case of major construction projects and in
situations where large number of re uses of the same forms are possible.
However, for small works involving less number of re uses, timber formwork
proves economical. Fibre glass is used mainly for making moulds for repetitive
castings of pre cast concrete products. Moulds made up of pre cast concrete,
fibre glass and aluminium are used in cast in situ construction such as waffle
slabs or members involving curved surfaces.
TIMBER FORMWORK
Timber used for the formwork should satisfy the following requirements:
· It should be well seasoned.
· It should be light in weight.
· It should be easily workable with
nails without splitting.
· It should be free from knots.
The sizes of timber sections for different components of form work depend
upon the span of the slab or beam, floor to floor height and the centre to
centre spacing of the centering supports.
The size of timber planks or joists that can be adopted for different
components of formwork for shuttering of 4.5 m span and 3.5 m height.
For normal construction work where repetitive use of shuttering is
possible, the quantity of timber shuttering can be worked out on the assumption
that one set of shuttering can be used 10 to 12 times.
The timber used for shuttering for exposed concrete work should have
smooth and even surface on all faces which are to come in contact with concrete
in situations, where concrete surfaces are not exposed, as in case of
foundation etc. undressed timber can be used to effect economy. The timber
planks for the shuttering should be joined by providing tongued and grooved
joints so as to ensure adequate tightness against leakage of cement grout.
PLYWOOD FORMWORK
Use of plywood instead of timber planks is getting popular these days. In
this case resin bonded plywood sheets are attached to timber frames to make up
panels of required sizes. The panels thus formed can be easily assembled by
blotting in the form of shuttering. This type of shuttering ensures quality
surface finish and is specially recommended in works where large exposed areas
of the concrete are to be constructed such as floor slabs, faces of retaining
walls etc.
· It is possible to have perfectly
plain and smooth surface by use of plywood shuttering.
· By use of large size panels it is
possible to effect saving in the labour cost of fixing and dismantling.
· Number of re uses are more as
compared with timber shuttering. For estimation purposes, number of re uses can
be assumed as 20 to 25.
STEEL FORMWORK
This consists of panels fabricated out of thin steel plates stiffened
along the edges by small steel angles. The panel units can be held together by
two or more clamps or bolts provided along each edge and the shuttering can be
assembled and kept in alignment by use of horizontal or vertical centering of
timber or steel. The panels can be fabricated in large number in any desired
modular shape or size. The usual size for wall or slab panel varies from 60 cm
x 60 cm x 120 cm.
Steel forms are mostly used in large construction projects or in
situations where large number of re uses of the same shuttering are possible.
Steel forms are extensively used in repetitive castings of pre cast concrete
products. This type of shuttering is considered most suitable for circular or
curved shaped structures such as tanks, columns, chimneys etc. and for
structures like large sewer, tunnels and retaining walls.
Although steel shuttering costs more initially but in view of its various
advantages it may work out to be economical for a medium sized work in the long
run.
Advantages of steel formwork over
timber forms:
· Steel forms are stronger, more
durable and have longer life s compared with timber forms.
· They can be put to sufficiently
larger number of re uses. For estimation purposes the number of re uses can be
assumed to vary from 100 to 120.
· Steel forms can be installed and
dismantled with greater ease and speed which results in saving in labour cost
for this item of work.
· There is no danger of the formwork
absorbing water from the concrete and hence the chances of honey combing are
minimized.
· They are not to shrink or distort and
hence it is possible to achieve better workmanship and higher degree of
accuracy by use of steel forms.
· The quality of exposed concrete
surface obtained by use of steel forms is excellent and it needs no further
treatment. On the other hand, construction carried out by use of timber
formwork invariably requires plastering to obtain desired finish of the concrete
surface. Thus there is saving in the cost of finishing the surface by use of
steel forms.
CONSTRUCTION OF FORMWORK
The construction of formwork normally involves the following operations:
1.Propping and Centering:
The props used for centering may be of steel, timber posts or bellies.
Pillars made up of brick masonry in mud mortar are also sometimes used as
props. In case wooden ballies are used as props, they should rest squarely on
wooden sole plates laid either on ground or on brick masonry pillars in mud
mortar. The wooden plate should have area at least 0.1 sq.m. and it should be
40 mm in thickness. Double wedges are essentially provided between the sole
plates and the timber props with a view to permit accurate adjustment of the
shuttering prior to concreting operation and to allow easy removal of
shuttering afterwards. In case brick masonry pillars are used at prop, the
wooden sole plates are provided at the top of the pillars, and the double
wedges are inserted the sole plates and the bottom of shuttering.
2. Shuttering:
The shuttering can be made up of timber planks, or it may be in the form
of panel units made either by fixing plywood to timber frames or by welding
steel plates to angle framing. In any case, the shuttering should be
constructed in such a manner that the joints should be tight against leakage of
cement grouts.
Sometimes, the Architect specifies provision of moulding in slab or
columns or provision of chamfers at corners of beams and columns. All such
mouldings, bevelled edges, chamfers etc., required to be formed in the concrete
work should be made in the shuttering itself. Similarly, the opening for fan
clamps or other fittings should be provided in the shuttering as per details in
the drawing.
3. Provision of camber:
Certain amount of deflection in structure in unavoidable. It is therefore
desirable to give an upward camber in the horizontal members of the concrete
structure to counteract the effect of deflection. The provision of desired
camber should be made in the formwork itself during its erection. Camber for
slabs and beams may be adopted @4 mm per metre of span. In case of cantilevers,
the camber at free end should be taken @ 1/50th of the projected
length of the cantilever.
4. Surface treatment:
Before laying concrete the formwork should be cleaned of all rubbish
particularly the sawdust shavings and chippings etc. All surfaces of timber
shuttering that are to come to contact with concrete should be well wetted with
water. This is necessary to prevent the chances of dry shuttering timber
absorbing water from the concrete which may cause warping, swelling and
distortion of timber besides resulting in defect of honeycombing in concrete.
Similarly steel forms that have been exposed to hot weather should be
cooled by watering before laying concrete.
In addition, all surfaces of shuttering which are to come in contact with
concrete should be given a good coating of raw linseed oil or soft soap
solution or any other material so as t prevent the concrete getting struck to
the formwork and thus facilitate easy removal. It is, however, important to
note that the coating should not come in contact with reinforcement. The
selected coating should be impermeable and should neither get flaky on exposure
to weather nor stain the surface of concrete.
ORDER AND METHOD OF REMOVING FORMWORK
The formwork should be planned and constructed in such a manner that it
is possible to remove the different components in the following order of
sequence:
· Shuttering forming vertical faces of
walls, beams and columns sides should be removed first.
· Shuttering forming soffit to slabs be
removed next.
· Shuttering forming soffit of beams,
girders or other heavily loaded shuttering should be removed in the end.
Duration of time up to which the formwork should be kept in place depends
upon many factors such as type of cement used, shape and position of the member
loads to be carried by the members and the temperature of the air. In general,
rapid hardening cement, warm weather and light loading conditions allow early removal
or formwork.
Early release of formwork permits its re use in other areas and this
results in economy by way of optimum utilisation of material and fast
construction. At the same time premature removal of formwork may prove to be
dangerous and should not be allowed.
The formwork should, under no circumstances, be allowed to be removed
until concrete reaches a strength of at least twice the stress to which the
concrete may be subjected to at the removal of formwork.
In normal conditions the formwork may be struck or removed after the
expiry of the period indicated against respective member.
All formwork should be eased gradually and carefully in order to prevent
the load being suddenly transferred to concrete. The forms can be easily
stripped by loosening the double wedges. Sometimes, the swelling of timber may
result in shuttering getting jammed at places. In such situation a mall crowbar
can be used to strike off the shuttering. In case of cantilever slabs and
beams, the centering should be removed only after necessary construction to
provide proper counterweight has been carried out and the same has attained
sufficient strength.

0 Comments